July 2020

– Fourth Street roadway extension continues
– Curbs and concrete being poured
– Extension of Fourth Street is underway
– Grading the roadway and preparing for concrete
June 2020

– Transformer pad inspected and approved by DTE
– Structural steel (heavy iron) delivered on site and is being erected
– Light gage CFS steel for the second floor is scheduled for delivery next week
May 2020

– Steel work continues at Fourth & Selden
– Second-floor light gage steel joists and decking are being installed
– Site work concrete for the dumpster enclosure, screen wall and transformer pad are underway
March 2020

– Transformer pad inspected and approved by DTE
– Structural steel (heavy iron) delivered on site and is being erected
– Light gage CFS steel for the 2nd floor is to be delivered the following week
– Podium steel construction has begun
– First steel members in place

+ South masonry shaft build is complete
+ Perimeter blocks being built
+ Site Storm and Sewer, including structures, are complete
+ Site primary power and low-voltage conduits installed, inspected and being backfilled
+ Temporary power installed and connected
+ Underground plumbing being installed
+ Sub-grading of parking lot is underway